Continuous Load
Continuous Load: The 125 Percent Rule, Worked Step by Step
A continuous load is one of the most reliable sources of lost points on an electrician exam. The rule itself is short: size for the noncontinuous load plus 125 percent of the continuous load. The trouble comes from applying it to the wrong number, or applying it twice. This guide walks through the rule, four worked examples, and the mistakes to watch for.
What counts as a continuous load
Article 100 defines a continuous load as one where the maximum current is expected to continue for three hours or more (see the Article 100 wording quoted by IAEI Magazine and Electrical Contractor Magazine). Three hours is the only test. Store lighting that stays on all day is continuous. A drill motor used for ten minutes is not.
Where the 125 percent appears
The same idea shows up in several places, each for a different part of the circuit:
- Branch-circuit conductors: 210.19(A)(1). The conductor ampacity is based on the noncontinuous load plus 125 percent of the continuous load.
- Branch-circuit overcurrent device: 210.20(A). The device rating is not less than the noncontinuous load plus 125 percent of the continuous load.
- Feeder conductors: 215.2(A)(1), with the overcurrent device covered in 215.3.
Subsection lettering and wording change between code editions, and this site does not pin its examples to one edition. The section numbers above are the ones reported by the continuous load summary for the 2017, 2020 and 2023 editions, and the 2026 NEC was issued in 2025. Read the text of the edition your state has adopted, and ask your authority having jurisdiction (AHJ) when something is unclear.
The basic formula
Write it once and use it every time:
Minimum rating = noncontinuous load + (1.25 x continuous load)
Only the continuous part gets the 1.25. If a question gives you a total load, find out how much of it runs for three hours or more before you multiply.
Worked example 1: a purely continuous load
A branch circuit feeds a 16 A load that runs all day.
- Continuous load: 16 A
- 16 x 1.25 = 20 A
- A 20 A breaker is a standard size, so the minimum overcurrent device is 20 A.
This is the familiar "80 percent" rule seen from the other side. Dividing by 1.25 is the same as multiplying by 0.80, so a 20 A breaker carries 16 A of continuous load, and a 50 A breaker carries 40 A.
Worked example 2: continuous plus noncontinuous
A feeder serves 40 A of continuous load and 32 A of noncontinuous load.
- Continuous part: 40 x 1.25 = 50 A
- Add the noncontinuous part: 50 + 32 = 82 A
- No 82 A standard rating exists. Table 240.6(A) lists the standard sizes, and the next one up is 90 A.
The calculated 82 A is the minimum. Whether you may round up to the next standard size depends on the conditions in 240.4(B), which include an 800 A limit and no more than one receptacle for cord-and-plug portable loads, as described in the EEPower branch-circuit article.
Worked example 3: sizing a conductor
A single-phase branch circuit carries a 38 A continuous load.
- 38 x 1.25 = 47.5 A minimum
- The EEPower article selects a 6 AWG TW copper conductor rated 55 A, with a 50 A circuit rating.
The conductor must meet 47.5 A at the termination temperature that applies to your equipment. Always look up the ampacity in Table 310.16 using the correct temperature column.
Worked example 4: how much can I actually run?
This is the reverse question and exams love it. A 30 A circuit supplies a continuous load. What is the largest continuous load?
- 30 x 0.80 = 24 A
Check it by running the formula forward: 24 x 1.25 = 30 A. If a problem adds a noncontinuous load on the same circuit, subtract it first, then divide what is left by 1.25.
The 100 percent rated exception
The 125 percent multiplier has an exception. Where the assembly, including the overcurrent devices protecting the branch circuit, is listed for operation at 100 percent of its rating, the overcurrent device rating may be not less than the sum of the continuous plus the noncontinuous load (see the exception quoted by IAEI Magazine for 210.20(A)). Most standard breakers are not marked this way. Unless the problem tells you the equipment is listed for 100 percent, use 125 percent.
Common mistakes
- Multiplying everything by 1.25. Only the continuous load gets it.
- Applying the factor twice. If you already sized the breaker at 125 percent, do not multiply the load again to check the conductor against the breaker.
- Forgetting derating. Temperature and conduit-fill adjustments apply to the conductor ampacity, and the adjusted value must still meet the 125 percent minimum. A conductor derated to 78 A is too small for an 82 A requirement, as the continuous load summary points out.
- Using the wrong direction. To find a maximum load from a breaker, multiply by 0.80. To find a minimum breaker from a load, multiply by 1.25.
- Skipping the three-hour test. A load that runs for two hours is not continuous under the definition.
Self-check
1. A 24 A continuous load and a 6 A noncontinuous load share a circuit. What is the minimum rating? 24 x 1.25 = 30, plus 6 is 36 A. The next standard size is 40 A.
2. What is the largest continuous load on a 40 A breaker? 40 x 0.80 = 32 A.
3. A load runs for 2.5 hours at a time. Is it continuous? No. The definition requires three hours or more.
Keep practicing
The 125 percent rule feeds directly into ampacity and derating problems and into the residential load calculation. For hands-on repetition, see the CircuitDrill course.
This guide is for study only. Code requirements depend on the edition adopted where you work, and your AHJ makes the final call. CircuitDrill is an independent study tool, not affiliated with NFPA, the National Electrical Code, or any state licensing board.
Frequently asked questions
What is a continuous load in the NEC?
Article 100 defines it as a load where the maximum current is expected to continue for three hours or more. Anything shorter is not continuous under that definition.
Why is a 20 A breaker limited to 16 A of continuous load?
The overcurrent device must be at least 125 percent of the continuous load. Working backward, 20 divided by 1.25 is 16 A, which is the same as 80 percent of the breaker rating.
Does the 125 percent factor apply to the noncontinuous load too?
No. Only the continuous load is multiplied by 1.25. The noncontinuous load is added at 100 percent.
Is there an exception to the 125 percent rule?
Yes. Where the assembly, including the overcurrent devices, is listed for operation at 100 percent of its rating, the factor is not required. Check the edition your state adopted and ask your AHJ.
Free
Get 5 worked problems right away
Voltage drop, conduit fill, box fill, Ohm's law and derating. One problem each, solved line by line. They open right after you sign up.
Voltage drop calculator with every step shown
Single-phase or three-phase, copper or aluminum, 14 AWG to 500 kcmil.